One of the new features of Project 2007 is a new type of resource called a Cost resource. Previously there was Work and Material resources. The Cost resource adds the ability account for costs on tasks that have no relationship to the Work assigned on the task.
You might be saying to yourself that Project already had a feature that allowed you to do this called Task Fixed Cost and that this feature has been around since Project 98 (or was it Project 4? I can't remember.) If you are saying this you are right. However, Fixed Cost only lets you account for one 'lump sum' of this kind of cost per task. It was not very good for situations where you had more than one kind of cost per task. Cost resources make it easy to have multiple non-work related costs on a task and keep track of them easily. Even better they allow you to keep track the amount of each kind of cost across all the tasks. For example, if you have two Cost Resources, Travel and Hardware you can assign them to many tasks and then using the Resource Usage view you can see quickly how much money is scheduled to be spent on Travel and Hardware across all your tasks. You can even use the Resource Usage view to adjust where across the duration of the task the cost associated with the cost resource falls.
Assigning costs to a cost resource is done the same way as Units are set for an assignment. In the Assign Resources dialog there is a new field called "Cost". It is only active for cost resources. When you assign a resource to a task you just enter the amount you want to represent for that cost resource and click 'Assign'.
This is pretty cool stuff!
Tags: Project 2007, Project 12
Glen,
Accounting Calenadars are coming in 2007 too!
:-)
Brian
Posted by: Brian Kennemer | Friday, April 14, 2006 at 11:54 PM
This does sound rather interesting. One of the main reasons I find managers not wanting to utilize project for costs is due to this reason...the inability of Project to properly categorize costs.
Looking forward to this.
Posted by: devnet | Friday, April 14, 2006 at 09:50 AM
Brian,
This feature will close the gap between discrete work and level of effort work (which traditionally was not held in the schedule).
Now ALL work and ALL costs will be in one place and in sync with the cost accounting system (Cost View in our case).
Now when the accounting calendar and the EV fixes come we'll be back in business here in aerospace.
Posted by: Glen B. Alleman | Friday, April 14, 2006 at 09:09 AM
That sounds great, as it could be the solution to a problem currently, where I want to have one task item for a piece of outsourced work, with the cost representing the total for the contract. this is OK for planning, but the problem comes when multiple payments are made on that contract over a period of time, and I want to track actual costs. Currently I can do the cost actuals only by making each payment a subtask, which is a PIA to manage - I have zillions of task items in my plans that are only there to represent single payments.
Posted by: Greg | Friday, April 14, 2006 at 08:35 AM